Project Highlights
Sector | railways and subways | |
Country | Sweden | |
Location | Gothenburg | |
Type of Contract | ECI (Early Contractor Involvment) | |
Contract value | EUR 241 million | |
Customer | Trafikverket | |
Contractor | JV of Astaldi (with a 40% share) with Gulermak (Turkey, 40%) and NCR (Sweden, 20%) | |
Progress | in progress | |
Construction | from 2017 |
Description
The contract entails the design and construction of a new underground station and a 1.5 km access tunnel. The customer is Trafikverket, Sweden’s national transport and infrastructures agency. The works are financed through EU and public funding.