Project Highlights
Sector | railways and subways | |
Country | Italy | |
Location | Bicocca – Catenanuova | |
Type of Contract | EPC | |
Contract value | EUR 186 million (of which 34.226% Astaldi share) | |
Customer | RFI | |
Contractor | Astaldi (with a 34.226% interest) as part of a JV with Salini Impregilo (51.308% ), SIFEL (7.327%) and CLF (7.139%) | |
Progress | in progress | |
Construction | from 2018 |
Description
The contract to lay a second track for the Bicocca-Catenanuova section of the Palermo-Catania high-speed railway line (Italy) entails the construction design and performance of works along a route running for approx. 38 kilometres. The works will have a duration of approx. 54 months, including 6 months for design activities.
The new infrastructure will ensure improvement of links within Sicily and its connection to Europe’s TEN-T system.